PROJECT DETAILS
Start date:
August 1, 2018
STATUS:
01 August 2021
Client
Valle Del Cauca
CONTRACT
CML 157 de 2018
PROJECT DESCRIPTION
Work Contract for the Realignment and Commissioning of the 12″ Polyduct, Design and Engineering, Mechanical, Civil, Geotechnical Construction and Drilling and Hot Tapping & Line Stop of Pipelines in the Mulaló – Loboguerrero Section.
SCOPE: Services Management, Purchasing Management, Equipment Rental; for the Construction of Mechanical and Civil Works for the Realignment and Commissioning of the 12″ Polyduct in the Mulaló – Loboguerrero Section.